20:00

Free Test
/ 10

Quiz

1/10
Once the project's WBS has been created what process may happen next?
Select the answer
1 correct answer
A.
Estimate activity resources
B.
Define activities
C.
Estimate activity durations
D.
Sequence activities

Quiz

2/10
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Select the answer
1 correct answer
A.
Precedence Diagramming Method
B.
Schedule network template
C.
Dependency determination
D.
Activity on the Node

Quiz

3/10
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?
Select the answer
1 correct answer
A.
Push technique
B.
Many-to-many
C.
One-to-one
D.
Pull technique

Quiz

4/10
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
Select the answer
1 correct answer
A.
Perform resource leveling for the project.
B.
Crash the project schedule.
C.
Fast track the project.
D.
Remove things from the project scope.

Quiz

5/10
The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
Select the answer
1 correct answer
A.
Activity list
B.
Milestone list
C.
Activity attributes
D.
Project document updates

Quiz

6/10
Examine the figure given below: Certification Exam PMI Scheduling Professional PMI PMI-PMI-SP 2-3583755149 If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
Select the answer
1 correct answer
A.
Three days
B.
One day
C.
Four days
D.
Zero days

Quiz

7/10
You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?
Select the answer
1 correct answer
A.
A significant point in the project
B.
A goal of reaching a significant delivery of project benefits by an identified date
C.
An imposed date for the project to reach a given point
D.
The completion of a project activity that is crucial to project completion

Quiz

8/10
You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?
Select the answer
1 correct answer
A.
Process boundaries
B.
Process configuration
C.
Targets for improved performance
D.
Identification of project risks

Quiz

9/10
George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?
Select the answer
1 correct answer
A.
.96
B.
-$77,800
C.
$-34,500
D.
-$13,800

Quiz

10/10
You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
Select the answer
1 correct answer
A.
It means the largest schedule variance you can have is five percent.
B.
It is the earned value divided by the planned value for your project.
C.
It is the expectation of management to be 95 on schedule at 95 percent of the project.
D.
It means you will need to earn at least 95 cents per dollar invested in the project.
Looking for more questions?Buy now

PMI Scheduling Professional Practice test unlocks all online simulator questions

Thank you for choosing the free version of the PMI Scheduling Professional practice test! Further deepen your knowledge on PMI Simulator; by unlocking the full version of our PMI Scheduling Professional Simulator you will be able to take tests with over 311 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 311 questions.

BUY NOW

What to expect from our PMI Scheduling Professional practice tests and how to prepare for any exam?

The PMI Scheduling Professional Simulator Practice Tests are part of the PMI Database and are the best way to prepare for any PMI Scheduling Professional exam. The PMI Scheduling Professional practice tests consist of 311 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The PMI Scheduling Professional database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with PMI Scheduling Professional Simulator will also give you an idea of the time it will take to complete each section of the PMI Scheduling Professional practice test . It is important to note that the PMI Scheduling Professional Simulator does not replace the classic PMI Scheduling Professional study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the PMI Scheduling Professional exam.

BUY NOW

PMI Scheduling Professional Practice test therefore represents an excellent tool to prepare for the actual exam together with our PMI practice test . Our PMI Scheduling Professional Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our PMI Scheduling Professional Simulator and how our unique PMI Scheduling Professional Database made up of real questions:

Info quiz:

  • Quiz name:PMI Scheduling Professional
  • Total number of questions:311
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the PMI Scheduling Professional exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our PMI Scheduling Professional Simulator.

Use our Mobile App, available for both Android and iOS devices, with our PMI Scheduling Professional Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all PMI Scheduling Professional practice tests which consist of 311 questions and also provide study material to pass the final PMI Scheduling Professional exam with guaranteed success. Our PMI Scheduling Professional database contain hundreds of questions and PMI Tests related to PMI Scheduling Professional Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW