Argument4
Which of the following are inputs to Activity Definition?
Select the answer
1 correct answer
A.
Project Scope Statement and Work Breakdown Structure
B.
Activity list and Arrow Diagram
C.
Change Requests Lists and Organizational Process Assets
D.
Project Management Plan and Resource Availability

Quiz

2/10
Argument0
The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?
Select the answer
1 correct answer
A.
10
B.
12
C.
14
D.
16

Quiz

3/10
Argument1
A weighting system is a tool for which area of Conduct Procurements?
Select the answer
1 correct answer
A.
Plan contracting
B.
Requesting seller responses
C.
Selecting seller's
D.
Planning purchase and acquisition

Quiz

4/10
Argument4
Which document defines how a project is executed, monitored and controlled, and closed?
Select the answer
1 correct answer
A.
Strategic plan
B.
Project charter
C.
Project management plan
D.
Service level agreement

Quiz

5/10
Argument0
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Select the answer
1 correct answer
A.
Risk and uncertainty increase; the cost of changes increases.
B.
Risk and uncertainty increase; the cost of changes decreases,
C.
Risk and uncertainty decrease; the cost of changes increases.
D.
Risk and uncertainty decrease; the cost of changes decreases.

Quiz

6/10
Argument1
Which tool or technique is used in the Plan Scope Management process?
Select the answer
1 correct answer
A.
Document analysis
B.
Observations
C.
Product analysis
D.
Expert judgment

Quiz

7/10
Argument2
The Perform Quality Assurance process occurs in which Process Group?
Select the answer
1 correct answer
A.
Executing
B.
Monitoring and Controlling
C.
Initiating
D.
Planning

Quiz

8/10
Argument3
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
Select the answer
1 correct answer
A.
Identify Risks
B.
Control Risks
C.
Plan Risk Management
D.
Plan Risk Responses

Quiz

9/10
Argument4
An input used in developing the communications management plan is:
Select the answer
1 correct answer
A.
Communication models.
B.
Enterprise environmental factors.
C.
Organizational communications,
D.
Organizational cultures and styles.

Quiz

10/10
Argument0
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Select the answer
1 correct answer
A.
Mandatory
B.
Discretionary
C.
Internal
D.
External
Looking for more questions?Buy now

Project Management Professional V5 Practice test unlocks all online simulator questions

Thank you for choosing the free version of the Project Management Professional V5 practice test! Further deepen your knowledge on PMI Simulator; by unlocking the full version of our Project Management Professional V5 Simulator you will be able to take tests with over 919 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 919 questions.

BUY NOW

What to expect from our Project Management Professional V5 practice tests and how to prepare for any exam?

The Project Management Professional V5 Simulator Practice Tests are part of the PMI Database and are the best way to prepare for any Project Management Professional V5 exam. The Project Management Professional V5 practice tests consist of 919 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The Project Management Professional V5 database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with Project Management Professional V5 Simulator will also give you an idea of the time it will take to complete each section of the Project Management Professional V5 practice test . It is important to note that the Project Management Professional V5 Simulator does not replace the classic Project Management Professional V5 study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the Project Management Professional V5 exam.

BUY NOW

Project Management Professional V5 Practice test therefore represents an excellent tool to prepare for the actual exam together with our PMI practice test . Our Project Management Professional V5 Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our Project Management Professional V5 Simulator and how our unique Project Management Professional V5 Database made up of real questions:

Info quiz:

  • Quiz name:Project Management Professional V5
  • Total number of questions:919
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the Project Management Professional V5 exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our Project Management Professional V5 Simulator.

Use our Mobile App, available for both Android and iOS devices, with our Project Management Professional V5 Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all Project Management Professional V5 practice tests which consist of 919 questions and also provide study material to pass the final Project Management Professional V5 exam with guaranteed success. Our Project Management Professional V5 database contain hundreds of questions and PMI Tests related to Project Management Professional V5 Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW